Construction Cost Litigation Lawyer | Getting paid for work already done
Summary
A construction cost dispute arises when the party who ordered work refuses to pay the full contract price, citing defects, incomplete scope, or disagreement over additional work. Under Korean law this is treated as a claim for the contract price under a construction contract (도급계약, 민법 제664조), and the outcome usually turns on which party can prove what was actually agreed and what was actually built. Because most disputes hinge on documentary evidence — contracts, change orders, site logs, photos — the strength of a claim is often decided before the lawsuit is even filed.
Civil · ConstructionApplicable law: Civil Act (민법), Framework Act on the Construction Industry (건설산업기본법)
Construction Cost Litigation | Who has to prove what
Construction cost cases are won or lost on documentation. Courts will not simply accept a contractor's invoice or an owner's complaint at face value.
The contractor must prove the work and its value
The party claiming unpaid fees must show that the contracted work was completed and what it is worth, typically through the written contract, a detailed cost breakdown (내역서), progress photos, and site supervision records. Courts often appoint a court-commissioned appraiser (감정인) to assess the value of completed work when the parties dispute the amount (민사소송법 제335조 관련 감정 절차).
Oral agreements are the most common failure point
Many construction disputes start because scope changes were agreed verbally on-site and never documented. Without a written change order or at least a text message/email trail, a contractor claiming additional payment for extra work faces a significant evidentiary disadvantage.
Interest and delay damages
If payment is wrongfully withheld, statutory interest can accrue on the unpaid amount from the due date, and if litigation is filed, the heightened statutory rate under the Act on Special Cases Concerning the Promotion of Recovery of Legal Money and Bonds applies from the date the lawsuit is served (소송촉진 등에 관한 특례법 제3조).
Construction Cost Litigation | Defect deductions and warranty claims
Owners frequently withhold part of the payment on the ground that the completed work has defects. This is one of the most litigated areas in construction disputes.
The owner's right to demand repair or a price reduction
If the completed work contains defects, the owner may demand that the contractor repair them, and may claim damages equivalent to the cost of repair instead of, or alongside, a reduction in the price (민법 제667조). This right does not automatically cancel the underlying obligation to pay for the parts of the work that are defect-free.
Defect liability period limits how far back a claim can reach
Claims based on defects are generally subject to statutory limitation periods depending on the type of structure and defect (민법 제671조), and separately the Framework Act on the Construction Industry sets warranty periods by construction type for licensed contractors (건설산업기본법 제28조). An owner who raises defect claims years after handover may find the claim time-barred.
Set-off in practice: partial withholding is common but risky for owners
Owners sometimes withhold the entire remaining balance to pressure the contractor into repairs, but courts scrutinize whether the amount withheld is proportionate to the actual repair cost. Over-withholding can itself expose the owner to a counterclaim for the excess plus delay interest.
Construction Cost Litigation | Additional work and change orders
Disputes over whether extra work was authorized, and at what price, are the single most common trigger for construction litigation.
Was the additional work actually ordered?
A contractor cannot unilaterally decide to do extra work and bill for it; there must be evidence that the owner (or its authorized site manager) requested or approved the change. Site diaries, supervisor sign-offs, and even KakaoTalk message threads are commonly submitted as evidence of approval.
Pricing the extra work when no price was agreed
When extra work was clearly performed but no price was fixed in advance, courts will often rely on an expert appraisal of reasonable cost, benchmarked against standard unit-cost tables (표준품셈) or comparable market rates, rather than accepting either party's unilateral figure.
Construction Cost Litigation | Securing payment before and during litigation
Winning a judgment is only half the battle if the owner has no assets left by the time the case ends. Securing the claim early is often as important as the merits.
Contractor's statutory lien on the building
A contractor who has not been paid may be entitled to a lien (유치권) over the building or site it worked on, allowing it to retain possession until payment is made, provided the requirements for a valid lien are met (민법 제320조). This is a powerful practical lever but is frequently disputed and requires careful handling to avoid claims of unlawful occupation.
Provisional attachment before filing suit
Before or alongside filing the main lawsuit, a creditor can apply for a provisional seizure (가압류) of the owner's bank accounts, real estate, or receivables to prevent asset dissipation while the case is pending. This step is often what actually secures recovery, since a favorable judgment against an asset-less debtor is difficult to enforce.
Construction Cost Litigation | From dispute to recovery
1
Initial review of contract and records We review the construction contract, cost breakdown, change orders, site records, and payment history to assess the strength of the claim or defense before any filing.
2
Demand and negotiation A formal payment demand or defect notice is often sent first, both to preserve the record and because many disputes resolve at this stage without litigation.
3
Provisional attachment / lien assessment If there is a risk the counterparty will dissipate assets, we evaluate whether a provisional seizure (가압류) or a construction lien (유치권) should be put in place before or alongside the main suit.
4
Filing suit and court-appointed appraisal Once filed, the court frequently appoints an appraiser to assess the value of completed work, additional work, or defects (감정) — this appraisal often becomes the decisive piece of evidence.
5
Judgment and enforcement After judgment, if payment is still not made voluntarily, we pursue compulsory execution against the debtor's assets, bank accounts, or receivables.
Construction Cost Litigation | How fees are calculated
Retainer (착수금) Generally set with reference to the amount in dispute (the unpaid construction cost claimed or the defect deduction contested) and the complexity of the evidentiary record, particularly whether expert appraisal will be required.
Contingency fee (성공보수) If applicable, calculated as a percentage of the amount actually recovered or successfully defended against, agreed in advance and confirmed in the retainer agreement.
Appraisal and expert costs (감정료) Court-appointed appraisals to value completed work, additional work, or defects involve separate appraiser fees, which are advanced by the requesting party and later allocated according to the outcome.
Provisional attachment / lien-related costs Filing a provisional seizure (가압류) typically requires a court deposit (공탁금) or guarantee insurance premium, which is a cost distinct from attorney fees and calculated based on the amount secured.
Enforcement costs If compulsory execution is needed after judgment, additional costs for asset investigation and execution procedures may apply.
※ Costs vary depending on case complexity and specific circumstances; exact fees will be provided during consultation. No specific outcome is guaranteed.
Construction Cost Litigation | Self-Check Before You Contact a Lawyer
1️⃣ For contractors chasing unpaid fees
Do you have a written contract or at least a written cost breakdown (내역서)?
Do you have evidence (photos, site logs, messages) showing the work was completed as described?
If additional work was performed, is there any written or message-based approval from the owner?
Has the owner made any partial payment that could be treated as an admission of the debt?
2️⃣ For owners disputing a payment demand
Have you documented the specific defects with photos and, ideally, a written notice to the contractor?
Do you have an estimate of the actual repair cost, rather than an arbitrary deduction?
Was the scope of work that was actually completed different from what was contracted?
Is there a risk the contractor will assert a lien (유치권) over the property?
3️⃣ Before filing a lawsuit
Is there a real risk the other party will dissipate or hide assets before judgment?
Have you calculated the exact amount owed, including any applicable delay interest?
Is expert appraisal likely to be necessary to establish the value of work or defects?
Do you know the other party's assets well enough to plan for enforcement after judgment?
4️⃣ For subcontractors dealing with non-payment up the chain
Who is your direct contractual counterparty — the general contractor or the project owner?
Is there any assignment of claims or direct payment arrangement that could let you claim against the owner directly?
Have you preserved records of your own subcontract scope and pricing separately from the main contract?
Frequently Asked Questions
Q. The client is refusing to pay the final balance, claiming there are defects. What can I do?
A. First, document the actual condition of the completed work with photos and a written response to the defect claims, since owners must show the deduction is proportionate to actual repair cost (민법 제667조). If the amount withheld is clearly excessive relative to any real defect, a lawsuit for the unpaid balance with a request for expert appraisal is often the most effective route.
Q. Can I get paid for extra work that was only agreed verbally on site?
A. Yes, but it is harder without written evidence. Courts will look at site diaries, text messages, photos of the extra work, and any conduct by the owner (such as making partial payments referencing the extra work) as circumstantial evidence that the work was authorized and should be paid for.
Q. How long do I have to file a claim for defects after the building was handed over?
A. The limitation period depends on the type of structure and defect under the Civil Act (민법 제671조), and licensed contractors are also subject to warranty periods set by construction type under the Framework Act on the Construction Industry (건설산업기본법 제28조). Because these periods vary significantly by structure type, the specific facts of the handover date and defect type need to be checked.
Q. Can I refuse to hand over the building until I get paid?
A. A contractor may be entitled to exercise a lien (유치권) over the property it worked on until payment is received, if the statutory requirements are met (민법 제320조), but this is frequently contested by owners and can expose the contractor to counterclaims if the lien is asserted improperly. Whether a valid lien exists depends heavily on how possession was maintained and whether the underlying claim is genuinely connected to the property.
Q. The other party has no money — is it even worth suing?
A. A judgment is only useful if there are assets to enforce against, so before or immediately after filing suit we typically evaluate whether a provisional seizure (가압류) of bank accounts, real estate, or receivables is appropriate to preserve recoverable assets while the case proceeds.
Q. Do I need an expert appraisal for every construction cost case?
A. Not always — if the amount and scope of work are clearly documented in the contract and both sides agree on what was built, appraisal may be unnecessary. Appraisal becomes important specifically when the parties dispute the value of completed work, the scope of additional work, or the cost of repairing defects.
Q. What happens if the general contractor doesn't pay, but I worked as a subcontractor?
A. Subcontractors generally must pursue the party they directly contracted with (usually the general contractor), though direct payment claims against the project owner may be possible in limited circumstances involving assigned claims or specific statutory protections for subcontractors under the Framework Act on the Construction Industry. The exact structure of the contract chain determines who can be sued.
Q. Is it better to negotiate first or file suit immediately?
A. It depends on the risk of asset dissipation and the counterparty's responsiveness; a written demand is usually sent first both to create a paper trail and because many disputes settle once the other side sees a firm, documented position. If there's a real risk that assets will be moved or hidden, provisional attachment should be considered in parallel with or even before the demand.
Q. Does a written contract have to exist for me to sue for unpaid construction fees?
A. No — a construction contract does not need to be in writing to be enforceable under Korean law, but without a written contract, proving the agreed price and scope of work becomes significantly harder and often requires other evidence such as invoices, bank transfer records, and communications with the other party.
법무법인 프런티어(이하 “사무소”)는 개인정보보호법에 따라 정보주체의 개인정보 및 권익을 보호하고 개인정보와 관련된 정보주체의 고충을 신속하고 원활하게 처리하기 위하여 본 개인정보 처리방침을 수립·공개합니다.
제 1 조 수집하는 개인정보의 항목, 목적, 방법
제 2 조 개인정보의 처리 및 보유기간
제 3 조 개인정보의 제3자 제공
제 4 조 개인정보 처리업무의 위탁
제 5 조 정보주체의 권리·의무 및 그 행사방법
제 6 조 개인정보의 파기
제 7 조 의견수렴 및 불만처리
제 8 조 개인정보 처리방침의 변경
제 9 조 개인정보의 안전성 확보 조치
제 1 조 (수집하는 개인정보의 항목, 목적, 방법)
① 게시판 글 작성 시 필수 항목에 대한 수집목적은 ‘별도의 구체적 상담을 위하여’이며 수집항목은 ‘이름, 이메일, 연락처’입니다.
② 전항 외에 고객의 서비스 이용 과정이나 요청 사항 처리 과정에서 ‘IP주소, 접속로그, 단말기 및 환경정보, 서비스 이용기록, 쿠키’와 같은 정보들이 자동으로 수집 및 저장될 수 있으며, 이 때의 수집목적은 ‘사용자 홈페이지 이용, 사이트 이용에 대한 문의 민원 등 고객 고충 처리’입니다.
③ 사무소는 ‘홈페이지 고객 문의/고충 처리 시 전화 또는 인터넷을 통한 상담’과 같은 방법으로 개인정보를 수집합니다
제 2 조 (개인정보의 처리 및 보유기간)
관계법령의 규정에 따라 개인정보를 보존하여야 하는 의무가 있는 경우가 아닌 한, 정보주체의 개인정보는 원칙적으로 해당 개인정보의 처리목적이 달성될 때까지 보유 및 이용되며, 그 목적이 달성되면 지체 없이 파기됩니다.
제 3 조 (개인정보의 제3자 제공)
사무소는 정보주체의 개인정보를 본 처리방침에서 명시한 목적에 한해서만 처리하며 정보주체의 사전동의가 있는 경우 또는 개인정보보호법 등 관계법령의 규정에 의거한 경우에만 개인정보를 제3자에게 제공합니다. 사무소는 현재 개인정보를 제3자에게 제공하지 않고 있습니다.
제 4 조 (개인정보 처리업무의 위탁)
사무소는 현재 귀하의 개인정보 보호를 위해 귀하의 개인정보를 직접 취급 관리하고 있습니다. 단, 향후 보다 전문적인 서비스를 제공하기 위하여 제3의 전문기관에 귀하의 정보를 위탁할 필요가 있다고 판단되는 경우, 귀하의 사전 동의 하에 개인정보에 대한 취급을 위탁할 수 있습니다.
제 5 조 (정보주체의 권리·의무 및 그 행사방법)
① 정보주체는 개인정보보호법 등 관계법령이 정하는 바에 따라 사무소에 대해 개인정보의 열람, 정정 및 삭제, 처리정지 요구 등 개인정보 보호 관련 권리를 행사할 수 있습니다.
② 제1항에 따른 권리행사는 정보주체의 법정대리인이나 위임을 받은 사람을 통해서도 할 수 있습니다. 다만, 이 경우에는 개인정보보호법 시행규칙에 따른 위임장을 사무소에 제출하여야 합니다.
③ 사무소는 정보주체의 권리행사에 대하여 개인정보보호법 등 관계법령이 정하는 바에 따라 지체 없이 조치하겠습니다.
제 6 조 (개인정보의 파기)
① 사무소는 원칙적으로 개인정보의 처리목적이 달성된 경우 등 그 개인정보가 불필요하게 되었을 때에는 지체 없이 해당 개인정보를 파기합니다.
② 사무소가 관계법령의 규정에 따라 개인정보를 파기하지 아니하고 보존하여야 하는 경우에는 해당 개인정보 또는 개인정보파일을 다른 개인정보와 분리해서 저장·관리 합니다.
③ 사무소는 파기사유가 발생한 개인정보를 선정하여 개인정보 보호책임자의 승인을 받아 해당 개인정보를 파기합니다.
④ 사무소는 파기하여야 할 개인정보가 전자적 파일 형태인 경우 복원이 불가능한 방법으로 영구 삭제하며, 이외의 기록물, 인쇄물, 서면, 그 밖의 기록매체인 경우 파쇄 또는 소각합니다.
제 7 조 (의견수렴 및 불만처리)
정보주체는 개인정보 보호 관련 문의, 불만처리, 피해구제 등에 관한 사항을 아래 개인정보 보호책임자 또는 담당부서에 문의하실 수 있습니다. 사무소는 정보주체의 문의에 대하여 신속하고 충분한 답변을 드릴 것입니다.
개인정보 보호 책임자 : 변호사
연락처 : 02.
제 8 조 (개인정보 처리방침의 변경)
사무소의 개인정보 처리방침은 관련 법령, 지침 및 사무소 내부규정에 따라 변경될 수 있으며, 개인정보 처리방침이 변경되는 경우 관련 법령이 정하는 방법에 따라 공개합니다.
제 9 조 (개인정보의 안전성 확보 조치)
사무소는 개인정보의 안전성 확보를 위해 다음과 같은 조치를 취하고 있습니다.
관리적 조치 : 내부관리계획의 수립 및 시행, 구성원에 대한 정기적인 개인정보 보호교육 등
기술적 조치 : 개인정보처리시스템 등의 접근권한 관리, 접근통제시스템 설치, 고유식별정보 등의 암호화, 보안프로그램의 설치 등
물리적 조치 : 전산실, 자료보관실 등 개인정보 보관장소에 대한 접근통제